WELTEC BIOPOWER modernizes 1-megawatt biogas plant in Australia

The output of the plant, which has two 530-kilowatt CHP units, covers the energy requirements of the biogas plant. The electricity generated is able to power both the facility itself and the sewage treatment plant, with excess energy is exported to the electricity grid. The plant has a processing capacity of 33,000 tons of organic waste from food processors and restaurants to generate around 7,500,000 kilowatt hours of energy per year. Accepted waste includes fats, oils, brewery and dairy residues, fruit and vegetables which are fed into the stainless steel containers. The plant has already won prestigious awards for its technology: These include the Premier‘s Sustainability Award for leading innovation and practice in Victoria and the Banksia Award for Leading in Circular Economy.


At the start of the maintenance work, the tanks will first be completely emptied. In addition, the roofs of the two 3,573 cubic meter stainless steel fermenters and internal plant components such as the agitator technology will be replaced. The plant will then be commissioned and operational management will be secured. The digester contents will be temporarily stored in the storage tank and material can be filled back into the tanks after the refurbishment so the plant can be up and running quickly. This saves resources and costs. In addition, it is easier to restart the biological process when the fermented material is immediately available. Last but not least, the processes also comply with occupational safety requirements, which are a high priority in Australia – especially when emptying and filling the tanks. WELTEC will also provide on-site staff training.


“WELTEC BIOPOWER has been a valued partner in our successful journey with our Wollert Facility. We value their commitment to safety and quality and have leveraged their expertise in mechanical and biological consulting over the lifespan of our facility,” emphasizes Stephanie Salinas, Manager Waste to Energy Services at YVW. “WELTEC can look back on extensive experience with such complex refurbishment projects. We are delighted that we have been able to enjoy the trust of our customers over such a long period of time,” says Vladimir Bogatov, Area Sales Manager Asia Pacific at WELTEC BIOPOWER. With more than 400 biogas plants planned and built worldwide and a strong service department, WELTEC has the necessary level of expertise for such modernizations. This experience is also valued Down Under to ensure that the plant operation remains flexible and continues to live up to its reputation as one of Australia‘s most innovative biogas projects in the future.

Back to top of page